Examine the sample project and interpret your decision points using schedule compression techniques, such as resource leveling, fast tracking, overtime, or crashing. In a Word document, answer the following questions.

1. How do you see the schedule health per SV? What would you recommend? (Approximately 200 words, 40 points)

2. How do you see the cost and budget health per CV? What would you recommend? (Approximately 200 words, 40 points)

3. What are the benefits of using indices (SPI/CPI) compared to variances (SV/CV)? (Approximately 100 words, 20 points)